| Jun 08 | Confirm fractional CSV/CSA + RA contractor (v3 required hire — W2) | ④ Pilot v3 |
| Jun 24 | Patent filing go/no-go check (auto-task) — SHIFTED from Jun 14 | ② Patent |
| Jun 26 | FD via IPflair, 2 batches: Jun 22 (P01·P02·P02b·P03) · Jun 26 (P04·P05·P09·P10); priority date + §39 clock per batch | ② Patent |
| Jun 26 | Phase-1A demo-pass gate (4 must-confirm-live items) | ③ Development |
| Jun 26 | GATE 1 — entity structure + instrument locked (no outreach before) | ① Investment |
| Jun 30 | G-JUN Go/No-Go · confirm full-stack build hand (v3 required hire — W5) | ④ Pilot v3 |
| Jul 06 | W6 KILL-CHECK — ≥2 red ⇒ narrow scope or re-baseline (binding) | ④ Pilot v3 |
| Jul 27 | §39 foreign-filing window clears — US vs PCT decision | ② Patent |
| Jul 31 | W9 — RC freeze + G-8 quality agreement SIGNED (hard gate) | ④ Pilot v3 |
| Aug (W10–13) | G-7 supplier assurance pack closure (populated continuously from W7) | ④ Pilot v3 |
| Sep 01 | Phase-2 verified-build gate (e-sig, AI audit, inspection export) | ③ Development |
| Sep 1–15 | Buffer (contingency only — not a baseline) | ④ Pilot v3 |
| 15 Sep | HARD BACKSTOP — unverified workflows defer to change-controlled wave | ④ Pilot v3 |
| Sep 30 | GATE 2 — ≥2 qualified LOIs or pivot to bridge | ① Investment |
| ~Day 90 | Pilot launch gate (F0 closed, ≥2 partners, mock audit pass) | ④ Pilot |
| Dec 2026 | PCT decision · GATE 4 close · first seed close target | ②① |
| Jun 15 2027 | Complete specifications due (§9(1)) — no slip | ② Patent |